DTEK

On 18 May, DTEK Kyiv Regional Grids specialists brought the lights 100% back in the Kyiv region freed from the aggressors on 2 April 2022. High-voltage and distribution networks belonging to the company supplied power to homes of 260 thousand families in 600 settlements. Specifically, in Bucha, Vyshhorod and Brovary districts that suffered the most.

Energy workers did their best to make sure that the work is completed within 45 days rather than 60 as announced earlier.

In the Kyiv region, where the energy infrastructure suffered heavy destruction, it has taken us only 45 days to accomplish this massive network restoration of such a scale that the Ukrainian energy sector has never experienced throughout its history.

Currently, the company continues to work daily to restore electricity supply, particularly in Donetsk region.